Google Halts Work on Belgian AI Data Centre After Inspectors Find Building Went Up Without a Permit
Google has halted construction of a large data centre in Belgium after regional inspectors found that a building of 30,000 square metres was almost finished even though the planning permission it depended on had been refused, according to Agence France-Presse.
The company confirmed on Saturday 28 November that it had stopped work at the site near Charleroi, two days after inspectors from the Walloon Region walked onto the construction site and ordered about 300 workers to down tools. A spokesperson told AFP: “We have halted works consistent with the direction from local authorities and pending additional guidance.”
The stop-work order is the second time in two months that a European government has halted work at a Google data centre site, and it lands in the middle of a wider argument across Europe about how much water and electricity the artificial intelligence boom is allowed to consume. Google is spending billions of euros to expand the computing capacity behind its cloud and AI services, and Belgium is one of its main data centre hubs on the continent. The dispute in Wallonia shows that the race to build that capacity is now running into planning law, drought and organised local opposition at the same time.
Regional officials have described the construction as a major offence and say a report is being sent to public prosecutors. Google has challenged the refusal of its amended permit before Belgium’s highest administrative court, with a hearing scheduled for 7 January 2027. Until that case is decided, the nearly finished building stands idle on a former mining site in the province of Hainaut, and the company has not said when, or whether, it will be completed.
What inspectors found on Thursday
Inspectors sent by the Walloon Region visited the site at the Ecopôle business park in Aiseau-Presles, about 15 kilometres west of Charleroi, on Thursday 26 November, according to the Belgian public broadcaster RTBF and AFP. The site covers around 50 hectares of a former coalmine and straddles the municipalities of Farciennes, Aiseau-Presles and Sambreville.
What they found, in the words of Raphaël Stokis, the regional civil servant responsible for planning permits and their enforcement, was a building of 30,000 square metres — three hectares — that was almost finished, with its structural shell closed, even though the permit had been refused by the minister. Stokis told RTBF that there were some 300 workers on site, to whom inspectors gave a verbal order to stop work. The Guardian, in a report by Jon Henley published on 27 November, quoted Stokis in English: “Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused.”
The verbal order was confirmed to Google in writing, according to The Guardian. A day later, on Friday 27 November, Nicolas Yernaux, a spokesperson for the Wallonia regional authorities, went further. He told AFP that officials had identified “a major offence: the illegal construction of a building covering three hectares”, and that a report alleging the offence was being submitted to public prosecutors.
The sequence matters because it shows the regional administration did not act on a technicality discovered in an office. Inspectors went to the site, saw a building that was nearly complete, and stopped the work in front of the workforce. The referral to prosecutors means the affair may not end with a planning dispute. It could become a criminal matter, although no charges have been announced and neither Google nor the Walloon authorities have said publicly whether the company faces fines.
Google’s response, when it came on Saturday, was short. The spokesperson told AFP that the company had halted works in line with the direction from local authorities and was awaiting further guidance, adding: “We have operated in Belgium for over 15 years and remain committed to complying with local laws.” The company has not publicly addressed the substance of the allegation that it kept building after the amended permit was refused.
A permit that was granted, appealed and then refused
The dispute is not about whether Google was allowed to build a data centre at Aiseau-Presles at all. It is about which version of the project it was allowed to build. The original plan, approved in 2024, covered three smaller data centre buildings cooled by air, with a combined capacity of 160 megawatts, according to Crypto Briefing, cited by several outlets covering the order. Construction began in April 2024.
The original permit came with conditions that reflected the direction of European policy on data centres. They included on-site solar panels, a requirement that 90 percent of the energy consumed on the site must be carbon-free by 2025 and 95 percent by 2030, and, crucially, that Google would have to move towards a more sustainable cooling system in future, reportedly switching from water-consuming technology to air cooling, according to Data Center Dynamics.
In 2025, Google applied to change the plan. Instead of three smaller buildings, it wanted to merge two of them into one much larger facility, and instead of air cooling it wanted to cool the servers with water drawn from the nearby River Sambre. The request covered a withdrawal of 600 cubic metres of water per hour, of which less than a quarter would be returned to the river, according to the Belgian news agency Belga.
The regional administration initially approved the amendment in April 2026. A month later, a local resident appealed against the decision. In August 2026, François Desquesnes, the Walloon minister for territory and infrastructure, refused the change. He pointed to the region’s strained water supply and the likelihood of more frequent droughts, and Belgian media reported that local opposition to drawing water from the Sambre had grown as severe droughts hit the region from the spring onwards.
The minister’s office has since made clear that the original 2024 permit for three smaller, air-cooled buildings remains valid, a position confirmed in an official response to the Walloon Parliament on 21 October. That detail is important, because it means Google’s position is not that it had no permission to build anything. It is that the building inspectors found on 26 November does not match the version of the project that is still permitted. The regional authorities say the building includes elements covered only by the revoked amendment.
Google challenged the minister’s refusal in October, appealing to the Council of State, Belgium’s highest administrative court. According to reporting based on the court filing, the company applied through its European subsidiary Crystal Computing on 17 October to have the refusal suspended and annulled. A hearing on the request for suspension is scheduled for 7 January 2027.
The river at the centre of the dispute
The Sambre is not a large river, and that is precisely why it matters. It runs past the Ecopôle site through an industrial region that has lived with water stress for years, and the spring and summer of 2026 brought an exceptionally hot and dry season to Wallonia. When Desquesnes refused the amended permit in August, he did so against that background, and he pointed to a precedent inside Google’s own Belgian operations to make the point.
Google already runs a large data centre campus at Saint-Ghislain, also in Hainaut, near Mons. According to Data Center Dynamics, the minister noted that the Saint-Ghislain project uses one billion litres of water a year for cooling, returning one quarter and evaporating the rest. For a region facing repeated drought, the prospect of a second large withdrawal from a smaller river was, in the minister’s judgement, too much.
The numbers in the Aiseau-Presles application underline why opponents were alarmed. A withdrawal of 600 cubic metres an hour is 14,400 cubic metres a day, or more than five million cubic metres a year if the system ran continuously, with less than a quarter of it returned to the river. The rest would be lost, mostly through evaporation in the cooling process. Supporters of the project argue that modern liquid cooling is more efficient than air cooling and that data centres can be designed to use water responsibly. Opponents reply that efficiency measured per unit of computing power is not the same as a small absolute demand on a river that is already under pressure.
This is the argument that has moved from technical journals into town halls across Europe. Data centres need enormous amounts of electricity and, in many designs, large volumes of water to carry heat away from the servers. As the AI boom has driven a rush to build new capacity, the question of where that water comes from, and who gets priority when supplies are short, has become a political question rather than an engineering one. In Wallonia, it was decided by a minister refusing a permit, and then by inspectors walking onto a building site.
How Greenpeace forced the issue
The halt did not come about because the regional administration was monitoring the site. It came about because Greenpeace Belgium was. The environmental group filed an urgent request with the regional authorities, using satellite images and drone footage to show that construction had continued even though the amended permit had been revoked in August, according to AFP and Crypto Briefing. Greenpeace announced the launch of an emergency procedure on Wednesday 25 November, a day before the inspectors arrived.
“That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs, a spokesperson for Greenpeace Belgium, in comments reported by Data Center Dynamics. “The consequences of the climate crisis will only increase. In this context, the construction of energy-guzzling data centers cannot remain under the radar. This must be the subject of a genuine societal debate, not of discreet agreements between industry and the government.”
Greenpeace has called the site illegal, and it linked the Aiseau-Presles project to Google’s water consumption at Saint-Ghislain. The group argued that the climate crisis would only get worse in the region and that “energy-guzzling behemoths” should not be built without scrutiny, according to AFP.
The episode is also a case study in how environmental campaigning has changed. Satellite imagery and consumer drones have given campaign groups a way to watch construction sites that once only regulators could monitor, and to publish the evidence in a form that is hard for either a company or an administration to ignore. Within days of Greenpeace publishing its material, the regional administration had sent inspectors to the site and stopped the work. The “Stop Data Center” collective of local opponents, which had campaigned against the project, was part of the same mobilisation.
It is worth noting what Greenpeace did not claim. The group did not say that Google had no permit at all. Its case was that the company was carrying on with work covered by a version of the permission that had been revoked. That distinction, between the original permit and the amended one, is the same distinction the regional authorities are now drawing, and it is likely to be the central question in the court case in January.
Google’s response and the court case
Google’s public position has been restrained. In late October, after confirming its appeal to the Council of State, a company spokesperson in Belgium said in a statement reported by Belga, translated from French, that Google was “committed to using water and electricity responsibly and efficiently” and wanted to keep talking with the authorities. After the stop-work order, the company’s Saturday statement to AFP confirmed the halt and restated its commitment to complying with local laws, without engaging with the allegation that it had built without a valid permit.
The court case will test two questions. The first is whether the minister was entitled to refuse the amended permit in August, given the drought and the water demands of the project. The second is what happens to a building that was largely constructed while that refusal was in force. The stop-work order is now in force, and none of the reports have said how long the halt could last. The key questions, as set out in the coverage of the order, are whether the Council of State reverses the minister’s refusal when it takes up the case in January, whether the nearly finished building can be completed or used under the original air-cooled permit or must wait for the court, and whether the regional authorities take further action over the work carried out after the August revocation.
Google is building the project through Crystal Computing, its European subsidiary, and the stakes for the company go beyond a single building. In 2025, Google expanded its investment plans to five billion euros, about 5.8 billion dollars, in cloud and AI infrastructure in Belgium over the next two years, according to Data Center Dynamics. Belgium is one of its main data centre hubs in Europe, and the Aiseau-Presles campus was meant to be a significant part of that expansion.
There is also a regulatory change that arrived in the middle of the dispute. On 12 November, Wallonia announced a framework requiring data centre projects with a capacity of at least 25 megawatts to secure a prior partnership agreement with the region, according to AI Affairs, which reported on the Guardian’s coverage. The framework suggests that the regional government intends to treat large data centres as a matter of negotiated regional policy, not simply as a planning application to be approved or refused on its technical merits.
The second halt in two months
The Belgian order is the second time in two months that a European government has stopped work at a Google data centre site, according to AFP. In October, authorities in Finland ordered work halted at two planned Google sites until required environmental impact assessments were finished. That disruption came shortly after another Google project in Finland was suspended after the company was accused of illegally felling some 250,000 trees at Muhos, with an investigation still ongoing, according to Data Center Dynamics.
Taken together, the cases show the pressure technology companies face in Europe as they race to build energy-hungry facilities. Local officials and environmental groups are paying closer attention to water use, land use and whether projects follow planning rules, and they are increasingly willing to use the powers they have. The pattern is not confined to Google, and it is not confined to Belgium. Across the continent, data centre proposals are running into grid constraints, water limits and organised opposition from residents who see little local benefit in facilities that employ relatively few people once built but consume large amounts of power and water.
The industry’s answer is that data centres are the factories of the AI age, that they bring investment, construction jobs and tax revenue, and that modern designs are far more efficient than the facilities built a decade ago. Google’s own argument in Belgium has been that it uses water and electricity responsibly and efficiently. The counter-argument, made by Greenpeace and by the Walloon minister, is that efficiency is not the same as sustainability when the absolute demand keeps growing, and that a region in drought is entitled to decide how its rivers are used.
There is also a tension that the Aiseau-Presles case brings into focus. The original 2024 permit required Google to move towards more sustainable cooling, and the company then applied to move in the opposite direction, from air cooling to water cooling, because liquid cooling is more effective for the dense, high-powered servers used in AI workloads. The technology that makes AI data centres possible is pushing them towards water, while the climate that makes water scarce is pushing regulators the other way. That contradiction is not going to be resolved by a single court hearing in January, but the hearing will decide what happens to one very large building in Wallonia.
Analysis: Why It Matters
The halt at Aiseau-Presles matters for reasons that go well beyond a planning dispute in a Belgian province, and the first of them is the simplest: a company as large and as legally sophisticated as Google built a 30,000-square-metre building that the authorities say it did not have permission to build, and kept building it for three months after the permission was refused. Either the company believed it was entitled to proceed under the original permit, or it calculated that the risk of being stopped was worth taking, or there was a genuine misunderstanding about what the refusal covered. None of those explanations is flattering, and Google has not offered one in public. The silence is itself significant, because it leaves the impression that the company treated the August refusal as a problem to be litigated rather than as an instruction to stop.
That impression is reinforced by the timeline. The amended permit was refused in August. Google appealed in October. Greenpeace published drone footage showing that construction had continued. Only then, in late November, did inspectors arrive and order the work to stop. For three months, a building rose on a site where the amended design had been refused, and the mechanism that finally stopped it was not the planning system but an environmental group with a drone. That is a failure of enforcement, and it raises a question that will outlast this case: if a project of this size can proceed for months after a refusal, how many smaller ones are doing the same without anyone watching?
The second reason the case matters is water. The AI boom is usually discussed in terms of electricity, chips and capital, but water is becoming the binding constraint in more and more places. A data centre that withdraws 600 cubic metres of water an hour from a river is not a minor consumer, and in a region that has suffered severe drought since the spring, it is a direct competitor with farmers, households and the river’s own ecology. The Walloon minister’s decision to refuse the permit on water grounds, and to cite Google’s own Saint-Ghislain consumption in doing so, turns an abstract debate about sustainability into a concrete allocation decision. Rivers do not have infinite capacity, and someone has to decide who gets the water. In Wallonia, for now, the answer is not Google.
The third reason is the precedent it sets for how Europe governs the AI infrastructure boom. Wallonia’s new framework, requiring large data centre projects to secure a prior partnership agreement with the region, is an attempt to move the decision from the planning office to the political level, where the trade-offs between investment, jobs, water and energy can be debated openly. Greenpeace’s demand for “a genuine societal debate, not discreet agreements between industry and the government” points in the same direction. The old model, in which a data centre was treated like any other industrial building, is breaking down, because data centres are not like other industrial buildings: they consume resources at a scale that affects whole regions, and they do so for the benefit of users who may live thousands of kilometres away.
There is also a lesson here for the technology companies themselves. The industry has spent years arguing that its data centres are efficient, carbon-free and good neighbours. Those claims are now being tested against observable facts: how much water a site actually uses, how much power it draws, and whether the company follows the rules when the rules go against it. A stop-work order and a referral to prosecutors do more damage to the industry’s credibility than any number of critical reports, because they suggest that the companies’ public commitments and their building-site behaviour are not the same thing. Google’s statement that it remains committed to complying with local laws will be judged not by its wording but by what happens next at Aiseau-Presles.
Finally, the case matters because of what it reveals about the balance of power between global technology companies and local government. Google is one of the largest companies in the world, investing five billion euros in Belgium, and it was stopped by a regional civil servant, a minister’s refusal and a campaign group with satellite images. That is not a story of a company being bullied. It is a story of democratic institutions working as they are supposed to, slowly and imperfectly, but working. The building was nearly finished before anyone stopped it, which shows the limits of those institutions. But it was stopped, which shows their reality.
The wider question is whether this pattern will repeat. Finland has already halted Google sites. Wallonia has now done the same. Other European regions are watching, and other companies are building. The AI infrastructure boom is not going to slow down, because the demand for computing power is still growing. But the Aiseau-Presles case suggests that the boom will have to negotiate its way through planning law, water limits and public consent, and that the negotiation will not always go the industry’s way.
What to watch next
The immediate date to watch is 7 January 2027, when the Council of State is scheduled to hear Google’s request for the suspension of the minister’s refusal. That hearing will not decide the whole case, but it will indicate whether the court thinks Google has an arguable claim that the refusal was unlawful, and whether work can resume in the meantime.
The referral to public prosecutors is the second thing to watch. If prosecutors decide to pursue the allegation of illegal construction, the affair moves from planning law into criminal law, and the consequences for Google could include fines and, more importantly, a formal finding that it built without permission. No timetable has been given for that decision.
The third question is practical: what happens to the building itself. It is nearly finished, but it cannot be completed or used under the amended design while the refusal stands. Whether it can be adapted to the original air-cooled permit, or must wait for the court, or must in some part be altered or demolished, has not been answered by any of the parties. Google has not said publicly whether the dispute will push back the site’s planned opening date.
Finally, watch Wallonia’s new framework for large data centres, and whether other regions follow it. If the requirement for a prior partnership agreement becomes the norm, the Aiseau-Presles case will be remembered not as an isolated planning row but as the moment when European regions started to treat AI infrastructure as a political decision rather than a technical one.
Sources
- Agence France-Presse, via Rapporteur: “Google halts construction of Belgian data centre on authorities’ order”
- Data Center Dynamics: “Construction paused at Google data center in Farciennes, Belgium”
- Economy Media: “Belgium Orders Google to Halt Data Center Work Over Revoked Permit”
- Agence France-Presse, via Europe Says: “Belgium forces Google to halt construction of a data centre”
- ITDaily: “Walloon Region halts construction of Google data centre in Farciennes”